|
Daily Journal
Fall 1997- September 1998 We spent months visiting log home companies and open
houses to learn how log homes were put together. We found out that hardly any two
companies do things alike. From the way they dry the logs to the way they fasten them
together. We even made a big list showing what each company did. We finally decided that
there may be no right or wrong way to do it. Most log home companies have been in business
for years. And they have developed a complete method that works successfully for them.
The most important thing you should consider
when "interviewing" a log home company is if they will be easy to do business
with. Since log homes require a lot of planning up front, you will likely be making a lot
of phone calls to the company to help you.
September 1998
18th - 20th Attended Log Home Living and Timber
frame show.
January 1999
Made final
changes to floor plan.
Shopped for cabinet prices. (decided we can build them for much less)
18th - Started title search for construction loan.
23rd - Started clearing trees and underbrush from site.
25th - Started appraisal process.
February 1999
4th - Cut down approximately 15 trees 
6th - Cut up some of the trees and burned brush
9th - Title search complete.
13th - Finished cutting up trees.
15th - Final blue prints completed and in the mail.
16th - Log Cam went Live!
19th - Final blue prints arrive in the mail.
22nd - Appraisal complete (Praise God! This took forever.)
March 1999
5th - Mortgage commitment letter sent to
construction loan bank.
16th - Signed const. loan, bldg. permit, & builder's risk insurance.
17th - Mailed milling payment to Battle Creek.
22nd - Broke Ground!!! Started digging basement. (Praise God!)
23rd - Finished digging basement. 
27th - Ran strings for footing preparation.
29th - Finished running strings for footing.
April 1999
5th - Ran strings for the piers (we forgot to
do this earlier).
9th - Footing was dug out.
14th - Poured footing.
22nd - Built basement walls
23rd - .Finished basement walls
28th - Began pouring concrete into block walls for
stability & put in anchor bolts.
29th - Finished pouring walls, put in gravel for floor, & septic pipe rough-in.
30th - Termite bond, spread gravel, & poured basement concrete floor.
May 1999
3rd - Received delivery order from Home Depot.
June 1999
2nd - Reviewed delivery order from Lowes.
14th - Received delivery of logs. Building crew
arrived & started subfloor.
15th - Finished subfloor.
All the sub-floor decking is in place.
We had hoped to start stacking a course or two of logs but we had an afternoon rain shower
so the building crew decided to call it a day and start them tomorrow. We were also
going to spray the sub-floor with Thompson's water seal to protect it from rain during
construction as well as when we wash down the logs after dry-in. But the rain showed
up just as I went for the sealer. Now we must let it dry good before we apply the
sealer.
16th - Started stacking the log shell.

Well the crew got a good start this morning
stacking the logs. But rain came about 1:30 and the crew went on home. They
started on the back and left sides of the house. Since the logs are all stacked
around the right side of the house and this is the closest to ground level they left this
end of the house open until the last moment to have a place to bring the logs in. We
have not back filled yet so they built a ramp to carry the logs by hand over to the
sub-floor. Along the back they are up to about 3 courses. The front left wall
is now at six courses. The rain left about 4:00 so we went out and started cleaning
up around the house.
17th - Continued stacking the log shell.
18th - Finished stacking the log shell.
Praise the Lord! The outer shell is
complete. So far we've not experience any major problems. Our basement walls
were off by 1/2 inch on one end and 1 inch the other direction on the opposite end.
But our building crew has made adjustments with the sub-floor to allow the log shell to go
up without flaw. They have already notched out the back wall for the 2nd floor
beams.
19th - Sealed subfloor with water seal to protect
from rain & washing down logs later.
21st - Built first floor interior walls and placed girders. Also purchased
materials to seal basement.
22nd - Started laying 2x6 V-joint tongue and groove for 2nd floor.
23rd - Finished tongue and groove for 2nd floor. Built shed dormer wall on back
side of house.
24th - Rained out.
25th - Set rafters and ridge beam length ways of the house.
26th - Went tub/shower shopping and bought shower unit for upstairs.
28th - Rained out.
29th - Built porch and support beams above porch.
30th - Set ridge beam and rafters in outset of front of house.
July 1999
1st - Started installing 1x6 v.joint tongue and
groove decking over porch area.
2nd - Started installing 1x6 v-joint tongue and groove decking over left side.
5th - Dug a ditch around footing and sprayed off mud build-up on footing.
8th - Finished installing 1x6 v-joint tongue and groove over the shed dormer.
9th - Framed the walls for the gable dormers.
10th - Sealed exterior of basement walls and installed drainage system.
11th - Back-filled basement.
12th - Rained out.
13th - Installed decking over gable dormers and started framing walls on 2nd floor.
14th - Installed siding on gable dormers and finished framing walls on 2nd floor.
15th - Installed siding on shed dormer, set a couple of windows, and some collar
ties.
16th - Installed siding on gable ends and set remainder of collar ties for roof.
17th - Ran wiring for lights that must be done before the metal roof is installed.
18th - Rested!
19th - Installed facia board. Trimmed up the eves. Finished building
front gable window area. Started building bay window tub wall in master bath.
20th - Finished bay window. Installed doors and windows. Built stairs and
balcony railings.
Well for the most part Battle Creek is done
today. We were missing a collar tie and a balcony post. They worked from 7:30
to 7:00 today to get finish. They have to start another house near Nashville
tomorrow. They will be back Saturday to install the missing parts. Now it is
our turn to get busy.
24th - Installed last collar tie and balcony post.
Started handcrafting the log stairs.
27th - Started plumbing rough-in.
29th - Finished most of plumbing rough-in. We needed the faucets picked out for
the tub/shower units. We also needed a platform built for the gas hot water
tank since it is next to the garage.
August 1999
2nd - Start installing metal roofing.
12th - Finished installing metal roofing.
15th - Finished handcrafting the log stairs from the 1st floor to the 2nd floor.
16th - Started cleaning all lumber and debris from inside of house to prepare for log
cleaning.
19th - Tested areas behind kitchen cabinets with bleach and water to remove rain
stains.
21st - Ran some more electrical wiring. Installed plastic over black board to
keep it from getting wet when we pressure wash.
24th - Started bleaching and pressure washing interior log walls.
25th thru Sept. 10th continued bleaching the interior of the
house. The walls went fairly quick. However when we started
doing the ceilings and the rafters it seemed like a snails pace. For
one we had to erect scaffolding and ladders plus spraying over your head not
only will give you a crick in your neck but will fill your face with
whatever you are spraying.
September 1999
18th - Wired main electrical breaker box to meter
box.
20th - Built pedestal for hot water tank and HVAC units to sit on in basement.
24th - Alabama Power hooked up our power.
25th - Cut trim to install fixed glass windows. Tested stain samples on log and
siding pieces.
27th - Moved lumber stacks into basement and cleaned up the yard.
29th - Installed fixed glass.
October 1999
Installed garage doors
Bought stain and pesticide for outside of logs
Installed hot water tanks and natural gas lines
Installed insulation
Installed metal duct work
Started building stairs going down to basement
Bought whirlpool tub
Set HVAC units
November 1999
5th - Started bleaching and pressure washing the
outside
Applied insecticide to outside of logs
Applied stain to outside of logs
Second and final building inspection passed
Natural gas meter installed
Main duct work installed
We now have heat
Started installing insulation
December 1999
Started installing duct work to room registers
22nd Started installing some tongue and groove
31st Ditches dug for water and sewer
January 2000
1st Installed water and sewer pipes in yard
and covered the ditches
Week of the 3rd - Finished installing all duct work
10th - Reinforced sagging wall and varnished whirlpool deck.
11th - Installed more tongue and groove (great room wall)
12th - More tongue and groove
14th - Installed more tongue and groove and started staining interior walls
15th - Continuing tongue and groove and staining
16th - Set the whirlpool tub into place
February 2000
9th - Hung drywall in upstairs rooms
16th - Mudded drywall. Finishing tongue & groove in utility room and stair well.
Start laying the pine flooring and ceramic tile downstairs
March 2000
27th - Started installing window trim.
April 2000
3rd - Started finishing wood floors.
May 2000
18th - Moved in!!!
We have finally moved in!!!
Praise God! However we are still not finished. After 14 and a
half months of hard work we couldn't stand it any longer. Although
we lived on-site, our mobile home just couldn't compare to living in our
log home. Most rooms are complete with the exception of interior
doors or a light fixture of something. The house is functional
except we are making do without kitchen cabinets until we can build them.
Plumbing, electrical, and gas is working. We still lack the part of
the air conditioning units that sit outside. We are going to get
those installed this weekend hopefully. And aside from a couple of
90 degree days it hasn't been to hot in the house with out it.
We did have a problem with
our appraisal at first. You see the original appraisal we had done
according to the blue prints came back real low. In fact it read
that the house was worth less than what it would cost to build by nearly
$10,000. We didn't worry about it too much a first. But when
we got near the end of completion we called the appraiser back to see
about appraising it again. He informed us that we did not need or
want another appraisal. That market conditions in the area had
worsened and we would get a lower appraisal than we got the
first time. We panicked because that would leave us owing a large
sum of money to the bank because we could not borrow enough to cover
construction costs. I know, in hind site we should have
researched this farther to begin with. Lesson learned.
However, we wish to thank God and all those who prayed for us in this
matter. We found another appraiser who used a little different
approach to the appraisal. Cost to build! The original
appraiser tried using comparisons of similar houses that sold in the area.
First, there are very few log homes in the area. None of which
"compare" to ours. Not bragging here - its just that he
didn't have anything to compare with. Anyway the new appraiser beat
the old appraisal by $53,000 as is! Even without the cabinets,
fireplace and extra room and bath in basement. Now we can close the
loan and take our time completing the rest.
I would also like to
recommend M&T Mortgage
(formerly Keystone Financial Mortgage) and thank them for first rate
customer service getting our long term loan. We actually called them
up and talked to Sandra Sanchez about our appraisal problem.
She didn't make us feel like our home was a barn like conventional lenders
did with our situation. When you mention "log home" you
would be surprised at the responses you get from conventional lenders.
She work for us to get us what we needed. And quick too. You
can call her at 1-877-536-5736. Tell her Jay & Carrie
sent you from the Log Cam.
20th - Added fill dirt around house. Cleaned construction debris
26th - Got final appraisal back. Much better than original.
Summary This has
been an enormous project for us. As you can see we broke ground on
March 22nd of 1999 and 14 months later, on May 18th, we were able to move
in. Keep in mind that as we moved in we had just enough complete to
satisfy the appraiser. In fact the appraiser could not appraise it
as complete. Fortunately our mortgage lender was willing to accept
the appraisal marked "as is". We
would not have been that far along if it weren't for the grace of God and
much help from family and friends. The
fact is that the day we got the great news of the final appraisal we
almost completely stopped working on the house for a while. We were
so exhausted and stressed from trying to complete the house we just needed
to take a break from it. And I'm so grateful to our construction
loaner officer who allowed us a year and a half on our construction
loan. Our lives are back to normal now
if you can call it that. We are enjoying living in our log
home. People keep asking us if we are finished with it. I tell
them that we will never be finished with it. But it is kind of a
hobby for us. We still have quite a long list of things to do as I
will list below. But we are just taking our time. Working on
the weekends when we are not taking time for ourselves. At least now
there is no deadline to beat. Things left
to finish
- Kitchen cabinets
- More Decks
- Installing Rock around the basement
block walls
- Installing a fireplace
- Landscaping
- Finishing rooms in basement
Thanks for visiting with us and be sure to see all
the photos on the Drawing Board.
The Log
Cam | Our Story | Daily Journal | Features |
Links | The Drawing Board
Copyright © 2004 JC Web Creations |